NC500 Installation
Fourteen installation steps from unboxing through final appearance confirmation.
← NC500 Installation & Commissioning Guide
Verify main unit, dust bin, pneumatic cylinder, covers, motor, leveling feet, and side panel after unboxing.

Level the host, mount the pneumatic cylinder, adjust three white press-plate screws, and connect cables/air lines.



Install control panel cantilever, bellows cover (green alignment marks), dust collection unit, and side panel.




Complete press plate/feed mechanism, internal adjustments, feed motor, ball screw/guides, final bolt check, and front appearance.