安装 · NN300 · 试机批量生产前连续试制 3–5 件并检验四角质量。NN300 安装试机与验收首次启动前必须在 IO 监控屏启用缺料与缺钉检测。← NN300 安装与调试指南Trial run procedureLoad one moulding display-face up for a single-piece trial before batch production.Material-Out Detection and Nail-Out Detection must be enabled on the IO Monitor screen before start.Enter IO Monitor via bottom navigationConfirm Material-Out and Nail-Out detections enabledPress green Start on HMIInspect nailing quality and four-corner jointsFig. 15 — IO MonitorFig. 16 — Start & E-stopOptional — frame collector & conveyorSkip this section if the collector/conveyor option was not purchased.Collector width clearance: 3–5 mm vs finished frame widthLength clearance: approx. 5 mm after magazine window adjustmentVerify red-line defect sensor stops the line (trigger once during trial)Fig. 18 — [Optional] Collector widthFig. 19 — [Optional] Lift platformFig. 20 — [Optional] ConveyorFig. 21 — [Optional] Red-line sensor验收 FAQWhat is the acceptance criterion for trial pieces?Four corners joint well with no missed or misaligned nails. Run 3–5 consecutive acceptable pieces before full production.What if the machine dry-fires?Stop immediately. Confirm Material-Out Detection is enabled and magazines are loaded before restarting.申请 NN300 调试支持继续阅读NN300 installation hubHMI commissioningMechanical setup完整手册下载 NN300 完整安装手册 (PDF)